[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90991,64,1,"单选题","下列关于双代号时标网络计划的说法中，不正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能够清楚地表明计划的时间进程，使用方便",false,{"key":16,"text":17,"correct":14},"B","能在图上直接显示出各项工作的开始与完成时间，工作的自由时差及关键线路",{"key":19,"text":20,"correct":21},"C","虚工作可以用水平方向的虚箭线表示",true,{"key":23,"text":24,"correct":14},"D","可以统计每一个单位时间对资源的需要量","在双代号时标网络计划中，虚工作必须以垂直方向的虚箭线表示。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]