[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90988":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90988,64,1,"单选题","在某工程网络计划中，工作H的最早开始时间和最迟开始时间分别为第20天和第25天，其持续时间为9天。该工作有两项紧后工作，它们的最早开始时间分别为第32天和第34天，则工作H的总时差和自由时差分别为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3天和0天",false,{"key":16,"text":17,"correct":14},"B","3天和2天",{"key":19,"text":20,"correct":14},"C","5天和0天",{"key":22,"text":23,"correct":24},"D","5天和3天",true,"工作H的最早开始时间为20天，最迟开始时间为25天，则其总时差＝最迟开始时间－最早开始时间＝25－20＝5天；本工作的自由差＝紧后工作的最早开始时间－本工作的最早开始时间－本工作的持续时间＝MIN（32,34）-20-9=3（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]