[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90985,64,1,"单选题","在工程网络计划中，判别关键工作的条件是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该工作与其紧后工作开始之间的时距最小",false,{"key":16,"text":17,"correct":14},"B","该工作与其紧前工作之间的时间间隔为零",{"key":19,"text":20,"correct":14},"C","该工作与其紧后工作之间的时间间隔为零",{"key":22,"text":23,"correct":24},"D","该工作最迟开始时间与最早开始时间的差值最小",true,"本题考核的是关键工作的确定。工作总时差最小的工作是关键工作。总时差=最迟开始时间-最早开始时间。所以D是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]