[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90983,64,1,"单选题","下列关于关键线路的说法，错误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由关键工作组成",false,{"key":16,"text":17,"correct":14},"B","总的工作持续时间最长",{"key":19,"text":20,"correct":21},"C","由工作时差最小的工作组成",true,{"key":23,"text":24,"correct":14},"D","可以用双线标注","工作总时差最小的工作是关键工作，关键线路由关键工作组成。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]