[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90982,64,1,"单选题","某工程程网络计划中，E工作的总时差为5天，自由时差为4天，在检查实际进度时发现该工作的持续时间延长了6天，则E工作的实际进度对其紧后工作的最早开始时间及总工期的影响是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","使其紧后工作的最早开始时间推迟2天，并使总工期推迟1天",true,{"key":16,"text":17,"correct":18},"B","使其紧后工作的最早开始时间推迟2天，并使总工期推迟2天",false,{"key":20,"text":21,"correct":18},"C","使其紧后工作的最早开始时间推迟2天，但不影响总工期",{"key":23,"text":24,"correct":18},"D","使其紧后工作的最早开始时间推迟1天，但不影响总工期","E工作推迟了6天，而总时差为5天，则工程总工期向后推迟6-5=1天；自由时差为4天，则紧后工作推迟6-4=2天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]