[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90981":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90981,64,1,"单选题","双代号网络计划中，工作N有四项紧前工作，其最早完成时间分别是第16周、第19周、第22周和第20周，则工作N的最早开始时间是第（ ）周。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":14},"B","19",{"key":19,"text":20,"correct":14},"C","20",{"key":22,"text":23,"correct":24},"D","22",true,"考察最早开始时间的确定。最早开始时间等于各紧前工作的最早完成时间的最大值。工作N有四项紧前工作，则N的最早开始时间＝MAX[16,19,22,20]=22.",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]