[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90980":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90980,64,1,"单选题","在工程网络计划中，工作F的最早开始时间是第8天，其持续时间为4天，该工作有三项紧后工作，其最迟开始时间分别为第15天、第17天、第20天，则工作F的总时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","10","最早完成时间=最早开始时间+持续时间=8+4=12天。最迟完成时间为各紧后工作的最迟开始时间的最小值，即15天；总时差=最迟完成时间-最早完成时间=15-12=3天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]