[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90978,64,1,"单选题","双代号网络计划中，工作H的持续时间是7天，最早完成时间是第13天，总时差是9天，则工作H的最迟开始时间为第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",true,{"key":16,"text":17,"correct":18},"B","16",false,{"key":20,"text":21,"correct":18},"C","20",{"key":23,"text":24,"correct":18},"D","22","最迟开始时间等于最迟完成时间减去其持续时间，即13+9－7＝15天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]