[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90977":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90977,64,1,"单选题","在工程网络计划中，工作M的最迟完成时间为第28天，其持续时间为6天。该工作有两项紧前工作，它们的最早完成时间分别为第12天和第15天，则工作M的总时差为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","8","考察总时差的计算。总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间，可知工作M的最早开始时间为MAX[12,15]=15（天），最总时差＝28－（15+6）＝7。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]