[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90975,64,1,"单选题","完成某工作的最短持续时间为8天、最长持续时间为16天、最可能持续时间为15天，则该工作的持续时间是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","16","本题考核的是双代号网络计划工作持续时间。记住“三时估算法”的公式就能很轻松地解答了：D=(a+4c+b)\u002F6=(8+4×15+16)\u002F6=14",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]