[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90971,64,1,"单选题","已标价工程量清单中没有适用也没有类似于变更工程项目，且工程造价管理机构发布的信息价格缺价的，由（ ）提出变更工程项目的单价，并报发包人确认后调整。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":14},"C","监理工程师或承包人",{"key":22,"text":23,"correct":24},"D","承包人",true,"考察工程变更的内容。合同中没有适用或类似于变更工程的价格，且工程造价管理机构发布的信息价格缺价的，由承包人提出变更工程项目的单价，并报发包人确认后调整。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]