[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90966":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90966,64,1,"单选题","假定某一建筑承包工程的结算价款总额为2000万元，预付备料款占价款的25%，主要材料和结构件金额占工程价款的62.5%。按照理论扣回方式，预付备料款起扣点是( )万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","500",false,{"key":16,"text":17,"correct":14},"B","800",{"key":19,"text":20,"correct":21},"C","1200",true,{"key":23,"text":24,"correct":14},"D","1500","考察预付款的起扣点的计算。直接代公式T=P-M\u002FN=2000－2000×25%\u002F62.5%=1200（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]