[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90961,64,1,"单选题","关于合同价款期中结算时工程计量的说法，正确的是( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对因承包人原因造成返工的工程量，发包人应适当予以计量",false,{"key":16,"text":17,"correct":14},"B","对承包人超出合同工程范围完成的工程量，发包人应适当予以计量",{"key":19,"text":20,"correct":14},"C","发包人需独立对工程进行计量，并完成已完工程量报告",{"key":22,"text":23,"correct":24},"D","承包人应当按照合同约定的方法和时间，向发包人提交已完工程量的报告",true,"AB选项内容，均不予以计量",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]