[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90959,64,1,"单选题","以一次包死的总价委托，价格不因环境的变化和工程量增减而变化，承包商承担了全部的工程量和价格变动风险的合同被称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价合同",false,{"key":16,"text":17,"correct":18},"B","固定总价合同",true,{"key":20,"text":21,"correct":14},"C","目标合同",{"key":23,"text":24,"correct":14},"D","成本加酬金合同","不可调值总价合同的价格计算是以图纸及规定、规范为基础，承发包双方就承包项目协商一个固定的总价，由承包方一笔包死，总价一笔包死，不能变化。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]