[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90958,64,1,"单选题","采用不可调值总价合同时，由发包方承担的是( )风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计和工程范围变更",true,{"key":16,"text":17,"correct":18},"B","地质条件不利",false,{"key":20,"text":21,"correct":18},"C","通货膨胀",{"key":23,"text":24,"correct":18},"D","施工质量不良","不可调值总价合同的价格计算是以图纸及规定、规范为基础，承发包双方就承包项目协商一个固定的总价，由承包方一笔包死，不能变化，只有在设计和工程范围有所变更的情况下才能做相应的变更，也就是说发包方只承担设计和工程范围变更的风险，而地质条件不利、通货膨胀、施工质量不良等风险均有承包方承担，故选A。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]