[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90956,64,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500--2008)，下列关于招标控制价的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标控制价是对招标工程限定的最高工程造价",true,{"key":16,"text":17,"correct":18},"B","招标控制价应在招标时公布，可以上调或下浮",false,{"key":20,"text":21,"correct":18},"C","在开标前，招标控制价必须保密",{"key":23,"text":24,"correct":18},"D","投标人的投标报价可高于招标控制价，但不应超过规定的比例","本题考核的是招标控制价的概念和意义。BCD的叙述均是错误的。招标控制价应在招标时公布，不应上调或下浮；在开标前，招标控制价一般是不需要保密的；投标人的投标报价高于招标控制价的，其投标应予以拒绝。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]