[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90955,64,1,"单选题","在工程量清单计价模式下编制投标报价时，措施项目费的报价原则是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目清单必须按照招标人所列措施项目填写",false,{"key":16,"text":17,"correct":18},"B","投标人可根据投标时拟定的施工组织设计或施工方案自主确定措施项目费",true,{"key":20,"text":21,"correct":14},"C","投标人必须按照招标人在措施项目清单中列出的单价确定措施项目费",{"key":23,"text":24,"correct":14},"D","投标人必须按照招标人在措施项目清单中列出的工程数量确定措施项目费","本题考核的是措施项目费的报价原则。投标人投标报价时，应根据招标文件中的措施项目清单及投标时拟定的施工组织设计或施工方案自主确定措施项目费。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]