[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90954,64,1,"单选题","在采用成本加酬金合同价时，为了有效地控制工程投资，最好采用（ ）确定的合同价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最高限额成本加固定最大酬金",true,{"key":16,"text":17,"correct":18},"B","成本加固定百分比酬金",false,{"key":20,"text":21,"correct":18},"C","成本加固定金额",{"key":23,"text":24,"correct":18},"D","成本加奖罚","最高限额成本加固定最大酬金可以最大限度地刺激承包商降低工程成本。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]