[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90951,64,1,"单选题","某工程合同价的确定方式为：发包方不需对工程量做出任何规定，承包方在投标时只需按发包方给出的分部分项工程项目及工程范围做出报价，而工程量则按实际完成的数量结算。这种合同属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","纯单价合同",true,{"key":16,"text":17,"correct":18},"B","可调工程量单价合同",false,{"key":20,"text":21,"correct":18},"C","不可调值单价合同",{"key":23,"text":24,"correct":18},"D","可调值总价合同","采用纯单价合同，发包方只向承包方给出发包工程的有关及分部分项工程及其工程范围，不需对工程量做出任何规定，承包方在投标时只需按发包方给出的分部分项工程项目及工程范围做出报价，而工程量则按实际完成的数量结算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]