[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90944,64,1,"单选题","下列关于成本加酬金合同的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","适用于工期较短的项目",false,{"key":16,"text":17,"correct":18},"B","适用于工程内容及其技术经济指标尚未全面确定的情况",true,{"key":20,"text":21,"correct":14},"C","适用于工程内容明确的情况",{"key":23,"text":24,"correct":14},"D","酬金金额必须事前固定，不得调整","成本加酬金合同适用于工程内容及其技术经济指标尚未全面确定的情况下，发包方因工期要求紧迫，必须发包的工程；或者发包方与承包方之间具有高度的信任，承包方在某些方面具有独特的技术、特长和经验的工程。一般有：成本加固定百分比酬金合同、成本加固定金额合同、成本加奖罚、最高限额成本加固定最大酬金合同四种。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]