[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90943,64,1,"单选题","在工程量清单计价模式下，关于投标人编制其他项目费报价的说法，正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","暂列金额应由投标人根据实际情况自主确定",false,{"key":16,"text":17,"correct":14},"B","材料暂估价应由投标人根据实际情况自主确定",{"key":19,"text":20,"correct":14},"C","专业工程暂估价应由投标人根据施工组织设计或施工方案自主确定",{"key":22,"text":23,"correct":24},"D","总承包服务费应由投标人根据招标文件中列出的内容和提出的要求自主确定",true,"关于A选项，暂列金额应按招标人在其他项目清单中列出的金额填写；关于选项B，材料暂估价应按招标人在其他项目清单中列出的单价计入综合单价，C选项，专业工程暂估价应按招标人在其他项目清单中列出的金额填写。D选项正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]