[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90942,64,1,"单选题","根据《建设工程工程量清单计价规范》，分部分项工程量清单的综合单价不应包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业管理费",false,{"key":16,"text":17,"correct":18},"B","规费",true,{"key":20,"text":21,"correct":14},"C","风险费用",{"key":23,"text":24,"correct":14},"D","利润","《建设工程工程量清单计价规范》中分部分项工程量清单的综合单价包括人工费、材料费、机械使用费、企业管理费、利润和一定的风险费用，但不包括规费和税金。所以应选B。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]