[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90941,64,1,"单选题","在工程量清单计价模式下，关于确定分部分项工程项目综合单价的说法，正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","若分部分项工程量清单项目特征的描述与设计图纸不符，投标人应按设计图纸确定综合单价",false,{"key":16,"text":17,"correct":14},"B","综合单价中不需考虑招标文件中要求投标人承担的风险费用",{"key":19,"text":20,"correct":14},"C","综合单价中应考虑招标人和投标人承担的所有风险费用",{"key":22,"text":23,"correct":24},"D","招标文件中提供了暂估单价的材料，应按暂估单价计入综合单价",true,"关于A，若分部分项工程量项目特征的描述与设计图纸不符，投标人应以招标文件描述的分部分项工程量清单项目特征确定综合单价；关于B、C，综合单价中应考虑招标文件中要求投标人承担的风险费用；D选项是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]