[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90935,64,1,"单选题","在施工图设计阶段，根据施工图纸确定的工程量，套用有关预算定额单价、取费率和利税率等编制( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设项目总概算",false,{"key":16,"text":17,"correct":14},"B","投资估算",{"key":19,"text":20,"correct":21},"C","施工图预算",true,{"key":23,"text":24,"correct":14},"D","建筑安装工程造价","在施工图设计阶段，根据施工图纸确定的工程量，套用有关预算定额单价、取费率和利税率等编制施工图预算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]