[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90927":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90927,64,1,"单选题","初步设计阶段编制工程概算，计算劳动、机械台班、材料需要量的依据是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","扩大指标",false,{"key":16,"text":17,"correct":14},"B","估算指标",{"key":19,"text":20,"correct":21},"C","概算指标",true,{"key":23,"text":24,"correct":14},"D","产值指标","概算指标往往是在初步设计阶段编制工程概算，计算劳动、机械台班、材料需要量的依据，若能够提供较为详细的项目资料，也可以依照概算指标编制投资估算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]