[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90925,64,1,"单选题","在固定资产投资估算编制方法中，根据已建成的类似项目的投资额、生产能力和拟建项目的生产能力，估算拟建项目投资额的方法是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资金周转率法",false,{"key":16,"text":17,"correct":14},"B","设备费用百分比估算法",{"key":19,"text":20,"correct":21},"C","生产能力指数法",true,{"key":23,"text":24,"correct":14},"D","造价指标估算法","本题考查考生对生产能力指数法定义的理解。生产能力指数法是根据已建成的类似项目的投资额、生产能力和拟建项目的生产能力，估算拟建项目投资额的方法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]