[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90920,64,1,"单选题","下列情形中，只能采用概算指标法编制建筑单位工程概算的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步设计深度不够，不能准确计算工程量，但工程采用的技术比较成熟且有类似概算指标可以利用",true,{"key":16,"text":17,"correct":18},"B","初步设计有一定深度，能计算出扩大的分部分项工程量",false,{"key":20,"text":21,"correct":18},"C","有详细的施工图设计资料，能准确计算分部分项工程量",{"key":23,"text":24,"correct":18},"D","没有初步设计资料，无法计算出任何工程量","本题考核的是建筑单位工程概算的编制方法。当初步设计深度不够，不能准确计算工程量，但工程采用的技术比较成熟且有类似指标可以利用时，可采用概算指标来编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]