[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90914,64,1,"单选题","依照《建设工程工程量清单计价规范》规定，以下关于工程量清单的说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量清单必须委托中介机构编制",false,{"key":16,"text":17,"correct":14},"B","措施项目清单列项内容主要包括预留金和零星工作项目费",{"key":19,"text":20,"correct":14},"C","其他项目清单列项内容主要包括利润和税金",{"key":22,"text":23,"correct":24},"D","工程量清单是招标文件的组成部分",true,"A工程量清单可以由招标人自己编制，也可以由委托中介机构编制。B暂列金额和零星工作项目属于其他项目清单，不属于措施费清单。C其他项目清单中包括暂列金额、暂估价、计日工、总承包服务费四项，利润无需列出，税金在税金项目清单中单列。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]