[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90913,64,1,"单选题","《建设工程工程量清单计价规范》中，分部分项工程量清单中，同一招标工程的项目编码( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不得有重复",true,{"key":16,"text":17,"correct":18},"B","可以有重复",false,{"key":20,"text":21,"correct":18},"C","可以有重复，但是需要做出说明",{"key":23,"text":24,"correct":18},"D","根据工程实际情况确定","考察项目编码的设置。分部分项工程量清单中，同一招标工程的项目编码不得有重复。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]