[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90910,64,1,"单选题","按照《建设工程工程量清单计价规范》规定，措施项目费( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应采用综合单价计价",false,{"key":16,"text":17,"correct":14},"B","应由招标人根据企业情况自行报价",{"key":19,"text":20,"correct":14},"C","应采用工料单价计价",{"key":22,"text":23,"correct":24},"D","应根据拟建工程的施工方案或施工组织设计，对其作出适当调整",true,"考察项目措施清单的编制。在编制措施项目清单时，因工程情况不同，出现计量规范目录中未列出的措施项目，可应根工程的具体情况对措施项目清单作补充。D的说法最符合题意，因此选项D正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]