[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90907,64,1,"单选题","分部分项工程量清单的项目编码采用12位阿拉伯数字表示，其中第10—12位表示的为( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专业工程顺序码",false,{"key":16,"text":17,"correct":14},"B","分部工程顺序码",{"key":19,"text":20,"correct":14},"C","分项工程名称顺序码",{"key":22,"text":23,"correct":24},"D","清单项目名称顺序码",true,"分部分项工程量清单项目编码采用五级编码：用12位阿拉伯数字自左至右表示，前两位：专业工程顺序码，三四位，附录分类顺序码，五六位，分部工程顺序码，789，表示分项工程名称顺序码，后三位，表示清单项目名称顺序码。故选D。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]