[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90906":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90906,64,1,"单选题","关于工程量清单的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取工程量清单招标时，必须将工程量清单作为招标文件的组成部分",true,{"key":16,"text":17,"correct":18},"B","工程量清单必须由投标人编制",false,{"key":20,"text":21,"correct":18},"C","工程量清单必须由招标人编制",{"key":23,"text":24,"correct":18},"D","工程量清单必须委托有资质的工程造价咨询人编制","清单编制应由（不是必须）具有编制能力的招标人编制，若不具备，可委托工程造价咨询人编制。所以BCD都不正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]