[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90901,64,1,"单选题","按照《建设工程工程量清单计价规范》规定，项目编码分五级设置。第5、6位数字是指( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部工程顺序码",true,{"key":16,"text":17,"correct":18},"B","清单项目名称顺序码",false,{"key":20,"text":21,"correct":18},"C","专业工程顺序码",{"key":23,"text":24,"correct":18},"D","分项工程名称顺序码","第一级编码表示专业工程顺序码，二级编码表示附录分类顺序码，三级编码表示分部工程顺序码；四级编码表示分项工程名称顺序码，五级编码表示清单项目名称顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]