[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90892":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90892,64,1,"单选题","暂列金额是指招标人在工程量清单中暂列并包括在合同价款中的款项，在工程量清单中应列入（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","措施项目清单",false,{"key":16,"text":17,"correct":14},"B","分部分项工程量清单",{"key":19,"text":20,"correct":14},"C","规费项目清单",{"key":22,"text":23,"correct":24},"D","其他项目清单",true,"其他项目费清单包括暂列金额、计工日和总承包服务费。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]