[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90859,64,1,"单选题","由于发包人或者监理工程师的指令增加工程量和附加工程，造成工期延长和费用增加时，承包人提出索赔属于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","默示索赔",false,{"key":16,"text":17,"correct":14},"B","反索赔",{"key":19,"text":20,"correct":14},"C","综合索赔",{"key":22,"text":23,"correct":24},"D","工程变更索赔",true,"本题考核的是建设工程施工合同索赔的类别。由于发包人或者监理工程师的指令增加工程量和附加工程，造成工期延长和费用增加，承包人对此提出的索赔属于工程变更索赔。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]