[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90835,64,1,"单选题","下列关于投标人的说法中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人应具备承担招标项目的能力",false,{"key":16,"text":17,"correct":18},"B","投标人可以补充、修改或撤回已提交的投标文件",true,{"key":20,"text":21,"correct":14},"C","投标人可以参加现场踏勘",{"key":23,"text":24,"correct":14},"D","投标人应制定对招标人有吸引力的施工方案","本题考核的是投标的要求和规定。B选项是错误的，应该是：投标人在招标文件要求提交投标文件的截止时间前，可以补充、修改或撤回已提交的投标文件。如果缺少这个前提，后面的一句话就是错误的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]