[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90814":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90814,64,1,"单选题","评标委员会完成评标后，应向( )提出书面评标报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":18},"B","招标人",true,{"key":20,"text":21,"correct":14},"C","监理机构",{"key":23,"text":24,"correct":14},"D","投标人","评标完成后，由评标委员会向招标人提出书面报告，并抄送有关行政监督部门。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]