[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90791,64,1,"单选题","建设项目的环境影响评价文件自批准之日起超过( )年，方决定该项目开工建设的，其环境影响评价文件应当报原审批部门重新审核。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","5",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]