[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90214,64,1,"单选题","根据表中给出的逻辑关系绘制的双代号网络图如下图所示，图中绘制的错误是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","逻辑关系表达不正确",false,{"key":16,"text":17,"correct":18},"B","节点编号有错误",true,{"key":20,"text":21,"correct":14},"C","出现了相同代号的工作",{"key":23,"text":24,"correct":14},"D","有多余的虚工作","在双代号网络图中，要求箭尾节点编号小于其箭头节点编号，故节点4和节点5的编号应互换。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]