[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90209":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90209,64,1,"单选题","在工程网络计划中，工作M有 B、 D、E三项紧前工作，其持续时间和工作最早开始时间如下表所示，则工作M的最早开始时间是第（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","22",{"key":19,"text":20,"correct":14},"C","24",{"key":22,"text":23,"correct":24},"D","26",true,"本题考査最早开始时间的计算。M工作的最早开始时间=max（8+16，5+17，6+20）=26（天） 某工作的最早开始时间是其所有紧前工作最早完成时间的最大值；某工作的最早完成时间=最早开始时间+持续时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]