[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},90172,64,1,"单选题","某分部工程双代号网络计划如下图所示，图中的错误是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","节点编号有误",true,{"key":16,"text":17,"correct":18},"B","工作代号重复",false,{"key":20,"text":21,"correct":18},"C","有多个起点节点",{"key":23,"text":24,"correct":18},"D","出现了没有外向箭线的节点","此题考查双代号网络图绘图规则。绘制双代号网络图应遵循的规则有：网络图中的节点都必须有编号，其编号严禁重复，并应使每一条箭线上箭尾节点编号小于箭头节点编号。本双代号网络图中⑥→⑤虚工作的箭尾节点编号大于箭头节点编号，故错误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]