[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-89295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},89295,64,1,"单选题","在工程网络计划中，工作M有 B、 D、E三项紧前工作，其持续时间和工作最早开始时间如下表所示，则工作M的最早开始时间是第( )天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","22",{"key":19,"text":20,"correct":14},"C","24",{"key":22,"text":23,"correct":24},"D","26",true,"工作M的最早开始时间=max（8+16,5+17,6+20）=26。@##",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]