[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1067418":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1067418,632,2,"多选题","提供劳务交易的履约进度，可以选择的确定方法有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术人员测量的完工进度",true,{"key":16,"text":17,"correct":18},"B","已经收到的款项比例",false,{"key":20,"text":21,"correct":14},"C","已经发生的成本的比例",{"key":23,"text":24,"correct":14},"D","采用投入的材料数量比例","ACD","采用投入的材料数量、花费的人工工时、机器工时、发生的成本和时间进度等投入指标确定恰当的履约进度。",{"id":6,"name":28,"category":29,"favorite":30},"卫生招聘 (财务)","医药卫生",0]