[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-81404":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},81404,62,2,"多选题","安装工程保险的保险期限的开始时间为（ ）起，两者以先发生者为准。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自被保险项目原材料等卸至工地",true,{"key":16,"text":17,"correct":18},"B","签发保险单次日0时",false,{"key":20,"text":21,"correct":14},"C","自工程破土动工之日",{"key":23,"text":24,"correct":18},"D","签发保险单之日24时",{"key":26,"text":27,"correct":18},"E","签发保险单之日12时","AC","在保单列明的起期日前提下，安装工程保险的保险责任开始有两种情况：自投保工程动工之日或自被保险项目卸至施工地点时起，两者以先发生者为准。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 保险专业","经济金融",0]