[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-80098":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},80098,62,1,"单选题","在安装工程保险中安装用机器、装置及设备，通常情况下是按（ ）收取保险费。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","年费率",true,{"key":16,"text":17,"correct":18},"B","工期一次性费率",false,{"key":20,"text":21,"correct":18},"C","固定费率",{"key":23,"text":24,"correct":18},"D","短期费率","安装工程险的费率主要由以下各项组成：①安装项目，土木建筑工程项目、所有人或承包人在工地上的其他财产及清理费为一个总的费率，整个工期实行一次性费率；②试车为一个单独费率，是一次性费率；③保证期费率，实行整个保证期一次性费率；④各种附加保障增收费率，实行整个工期一次性费率；⑤安装、建筑用机器、装置及设备为单独的年费率；⑥第三者责任险，实行整个工期一次性费率。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 保险专业","经济金融",0]