[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-80061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},80061,62,1,"单选题","建筑工程保险责任开始的时间是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自工程破土动工之日",false,{"key":16,"text":17,"correct":14},"B","建筑工程完毕移交所有人时",{"key":19,"text":20,"correct":14},"C","自被保险项目原材料等卸至工地时起",{"key":22,"text":23,"correct":24},"D","以AC选项中先发生者为准",true,"建筑工程保险责任的开始时间有两种情况：自工程破土动工之日或自被保险项目原材料等卸至工地时起，两者以先发生者为准。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 保险专业","经济金融",0]