[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-78359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},78359,62,1,"单选题","建筑工程保证期责任加保办法是（ )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有限责任保证期和扩展责任保证期",true,{"key":16,"text":17,"correct":18},"B","有限责任保证期和无限责任保证期",false,{"key":20,"text":21,"correct":18},"C","扩展责任保证期和原材料运至工地责任保证期",{"key":23,"text":24,"correct":18},"D","建筑动工责任保证期和原材料卸自工地责任保证期","工程完毕后，一般还有一个保证期，在保证期间如发现工程质量有缺陷甚至造 成损失，根据承包合同承包人须负赔偿责任，这是保证期责任。保证期责任加保与否， 由投保人自行决定，但加保则要加交相应的保费。保证期责任加保有两种方法：有限 责任保证期和扩展责任保证期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 保险专业","经济金融",0]