[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-608-4":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":667},{"id":5,"name":6,"category":7,"favorite":8},608,"项目决策分析与评价","建筑工程",0,4,50,1135,[13,38,52,64,76,88,100,112,124,136,148,160,172,183,198,210,222,234,249,264,273,285,299,314,326,338,350,365,380,392,401,413,428,441,456,471,485,497,509,521,533,545,557,569,581,595,609,623,638,653],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},940830,2,"多选题","可行性研究报告市场预测分析中，市场风险分析包括()。",[19,23,27,30,33],{"key":20,"text":21,"correct":22},"A","编制风险报告",false,{"key":24,"text":25,"correct":26},"B","识别风险因素",true,{"key":28,"text":29,"correct":26},"C","估计风险程度",{"key":31,"text":32,"correct":26},"D","提出风险对策",{"key":34,"text":35,"correct":22},"E","收集风险信息","BCD","",{"id":39,"libraryId":5,"type":40,"typeLabel":41,"stem":42,"options":43,"answer":24,"analysis":37},940831,1,"单选题","下列关于建设项目产品方案的说法，正确的是()。",[44,46,48,50],{"key":20,"text":45,"correct":22},"产品方案与技术装备、原材料供应方案无关",{"key":24,"text":47,"correct":26},"产品方案包括产品质量标准和产品规格等",{"key":28,"text":49,"correct":22},"有些项目生产多种产品，但主导产品只能有一种",{"key":31,"text":51,"correct":22},"产品方案是产品组合研究的基础",{"id":53,"libraryId":5,"type":40,"typeLabel":41,"stem":54,"options":55,"answer":31,"analysis":37},940832,"产品方案是指拟建项目的主要产品、辅助产品或附产品及其生产能力的组合方案。产品方案研究的内容通常不包括()。",[56,58,60,62],{"key":20,"text":57,"correct":22},"主要产品品种",{"key":24,"text":59,"correct":22},"产品年产量",{"key":28,"text":61,"correct":22},"产品用途",{"key":31,"text":63,"correct":26},"生产设备",{"id":65,"libraryId":5,"type":40,"typeLabel":41,"stem":66,"options":67,"answer":31,"analysis":37},940833,"在多套工艺装置中，“三废”排放与预处理不包括()。",[68,70,72,74],{"key":20,"text":69,"correct":22},"废气",{"key":24,"text":71,"correct":22},"废水",{"key":28,"text":73,"correct":22},"固体废物",{"key":31,"text":75,"correct":26},"灰尘和噪声",{"id":77,"libraryId":5,"type":40,"typeLabel":41,"stem":78,"options":79,"answer":28,"analysis":37},940834,"生产工艺技术方案和设备方案的选择是()确定的基础。",[80,82,84,86],{"key":20,"text":81,"correct":22},"建设规模和产品方案",{"key":24,"text":83,"correct":22},"总图运输和装备方案",{"key":28,"text":85,"correct":26},"工程和配套方案",{"key":31,"text":87,"correct":22},"建设条件与场址",{"id":89,"libraryId":5,"type":40,"typeLabel":41,"stem":90,"options":91,"answer":24,"analysis":37},940835,"国务院《关于投资体制改革的规定》，要求对()政府投资项目加快实行代建制。",[92,94,96,98],{"key":20,"text":93,"correct":22},"对采用直接投资方式的经营性",{"key":24,"text":95,"correct":26},"对采用直接投资方式的非经营性",{"key":28,"text":97,"correct":22},"对采用资本金注入方式的经营性",{"key":31,"text":99,"correct":22},"对采用资本金注入方式的非经营性",{"id":101,"libraryId":5,"type":40,"typeLabel":41,"stem":102,"options":103,"answer":28,"analysis":37},940836,"下列关于可行性研究中投资估算作用的说法，错误的是()。",[104,106,108,110],{"key":20,"text":105,"correct":22},"投资估算是制定项目融资方案的依据之一",{"key":24,"text":107,"correct":22},"投资估算是进行项目经济评价的基础",{"key":28,"text":109,"correct":26},"投资估算是编制施工图预算的依据",{"key":31,"text":111,"correct":22},"投资估算是投资决策的依据之一",{"id":113,"libraryId":5,"type":40,"typeLabel":41,"stem":114,"options":115,"answer":28,"analysis":37},940837,"以下关于规模总投资的说法，正确的是()。",[116,118,120,122],{"key":20,"text":117,"correct":22},"规模总投资即项目总投资",{"key":24,"text":119,"correct":22},"规模总投资包括建设投资、建设期利息和流动资金",{"key":28,"text":121,"correct":26},"财务分析中都采用项目总投资概念",{"key":31,"text":123,"correct":22},"经济分析中都采用规模总投资概念",{"id":125,"libraryId":5,"type":40,"typeLabel":41,"stem":126,"options":127,"answer":31,"analysis":37},940838,"为便于计算费用与效益，一般副产品回收计入()中。",[128,130,132,134],{"key":20,"text":129,"correct":22},"期间费用",{"key":24,"text":131,"correct":22},"固定资产折旧",{"key":28,"text":133,"correct":22},"其他营业费用",{"key":31,"text":135,"correct":26},"销售收入",{"id":137,"libraryId":5,"type":40,"typeLabel":41,"stem":138,"options":139,"answer":28,"analysis":37},940839,"项目经济分析的作用是()。",[140,142,144,146],{"key":20,"text":141,"correct":22},"促进企业利益与国家利益完全一致",{"key":24,"text":143,"correct":22},"促进稀缺货源在市场中均衡流动",{"key":28,"text":145,"correct":26},"正确反映项目对社会福利的净贡献",{"key":31,"text":147,"correct":22},"为企业合理配置自身资源提供依据",{"id":149,"libraryId":5,"type":40,"typeLabel":41,"stem":150,"options":151,"answer":20,"analysis":37},940840,"经济分析是按合理配置资源的原则考察项目的经济合理性，下列关于经济分析作用的说法，错误的是()。",[152,154,156,158],{"key":20,"text":153,"correct":26},"通过经济分析可以明确项目对社会经济的贡献，评价项目的财务合理性",{"key":24,"text":155,"correct":22},"根据经济分析结论政府可对财务效益好经济效益差的项目进行限制",{"key":28,"text":157,"correct":22},"根据经济分析结论政府可对财务效益差经济效益好的项目予以鼓励",{"key":31,"text":159,"correct":22},"根据经济分析结论对项目进行调控有助于实现企业利益和全社会利益的有机结合",{"id":161,"libraryId":5,"type":40,"typeLabel":41,"stem":162,"options":163,"answer":31,"analysis":37},940841,"当项目效果不能或难于货币量化时，或货币量化的效果不是项目目标的主体时，在经济分析中可采用()方法，并将其结论作为项目投资决策的依据。",[164,166,168,170],{"key":20,"text":165,"correct":22},"有无对比分析",{"key":24,"text":167,"correct":22},"敏感性分析",{"key":28,"text":169,"correct":22},"偿债能力分析",{"key":31,"text":171,"correct":26},"费用效果分析",{"id":173,"libraryId":5,"type":40,"typeLabel":41,"stem":174,"options":175,"answer":28,"analysis":37},940842,"在使用成本和费用估算的方法的时候，期间费用不包括()。",[176,178,180,182],{"key":20,"text":177,"correct":22},"其他管理费用",{"key":24,"text":179,"correct":22},"财务费用",{"key":28,"text":181,"correct":26},"折旧费用",{"key":31,"text":133,"correct":22},{"id":184,"libraryId":5,"type":15,"typeLabel":16,"stem":185,"options":186,"answer":197,"analysis":37},940843,"下列指标中，属于偿债能力分析指标的是()。",[187,189,191,193,195],{"key":20,"text":188,"correct":22},"资本金净利润率",{"key":24,"text":190,"correct":22},"内部收益率",{"key":28,"text":192,"correct":22},"累计盈余资金",{"key":31,"text":194,"correct":26},"借款偿还期",{"key":34,"text":196,"correct":26},"偿债备付率","DE",{"id":199,"libraryId":5,"type":40,"typeLabel":41,"stem":200,"options":201,"answer":24,"analysis":37},940844,"改、扩建和技术改造项目需要了解或估算五套。其中，“有项目”投资是指“有项目”时，拟建项目范围内的()加上项目范围内可利用的原有固定资产价值之和。",[202,204,206,208],{"key":20,"text":203,"correct":22},"“现状”数据",{"key":24,"text":205,"correct":26},"“新增”投资",{"key":28,"text":207,"correct":22},"“无项目”投资",{"key":31,"text":209,"correct":22},"“增量”投资",{"id":211,"libraryId":5,"type":40,"typeLabel":41,"stem":212,"options":213,"answer":24,"analysis":37},940845,"根据项目性质，对于政府投资项目，应按照有关规定编制项目代建制内容。具体内容不包括()。",[214,216,218,220],{"key":20,"text":215,"correct":22},"代建方式的确定",{"key":24,"text":217,"correct":26},"主要问题及建议",{"key":28,"text":219,"correct":22},"代建单位的选择标准及要求",{"key":31,"text":221,"correct":22},"不予招标或不宜招标的说明",{"id":223,"libraryId":5,"type":40,"typeLabel":41,"stem":224,"options":225,"answer":31,"analysis":37},940846,"在地质灾害易发区内进行工程建设，应在项目决策分析与评价阶段进行地质灾害危险性评估。地质灾害危险性评估的内容不包括()。",[226,228,230,232],{"key":20,"text":227,"correct":22},"工程建设诱发地质灾害的可能性",{"key":24,"text":229,"correct":22},"对可能的地质灾害危害拟采取的防治措施",{"key":28,"text":231,"correct":22},"工程建设本身可能遭受地质灾害的危险性",{"key":31,"text":233,"correct":26},"工程建设抑制地质灾害发生的可能性",{"id":235,"libraryId":5,"type":15,"typeLabel":16,"stem":236,"options":237,"answer":248,"analysis":37},940847,"在研究确定()的同时，要明确项目所需主要原材料和燃料的品种、数量、规格、质量的要求，对价格进行分析研究，并结合场址方案的比选确定其供应方案。",[238,240,242,244,246],{"key":20,"text":239,"correct":26},"建设规模",{"key":24,"text":241,"correct":22},"总图运输",{"key":28,"text":243,"correct":26},"产品方案",{"key":31,"text":245,"correct":22},"建设条件",{"key":34,"text":247,"correct":26},"工艺技术方案","ACE",{"id":250,"libraryId":5,"type":15,"typeLabel":16,"stem":251,"options":252,"answer":263,"analysis":37},940848,"关于项目可行性研究报告中全厂运输的说法，正确的有()。",[253,255,257,259,261],{"key":20,"text":254,"correct":22},"工厂内不应建设铁路运输设施",{"key":24,"text":256,"correct":22},"全厂运输应全部依托合建运输力量",{"key":28,"text":258,"correct":26},"全厂运输量表中应说明货物的包装方式",{"key":31,"text":260,"correct":22},"厂区内应考虑人流和货流同道以节省土地",{"key":34,"text":262,"correct":26},"易燃、易爆物品运输应制定特别运输方案","CE",{"id":265,"libraryId":5,"type":40,"typeLabel":41,"stem":266,"options":267,"answer":20,"analysis":37},940849,"工程和配套方案与项目的技术方案和设备方案以及()选择形成互为条件，也是投资估算和经济分析的重要基础，是影响项目环境、安全等以及经济合理性的重要因素。",[268,269,270,272],{"key":20,"text":81,"correct":26},{"key":24,"text":83,"correct":22},{"key":28,"text":271,"correct":22},"财务分析和风险分析",{"key":31,"text":87,"correct":22},{"id":274,"libraryId":5,"type":40,"typeLabel":41,"stem":275,"options":276,"answer":28,"analysis":37},940850,"关于工程方案中防震抗震编制内容及要求的说法，正确的是()。",[277,279,281,283],{"key":20,"text":278,"correct":22},"抗震设防是指建筑物的设防",{"key":24,"text":280,"correct":22},"抗震措施应结合工程结构特征，不考虑地质特征",{"key":28,"text":282,"correct":26},"需提出设计基本地震加速度",{"key":31,"text":284,"correct":22},"工业项目厂址不应选择在需要地震设防的地区",{"id":286,"libraryId":5,"type":15,"typeLabel":16,"stem":287,"options":288,"answer":36,"analysis":37},940851,"工程方案及配套工程方案中防震抗震编制的内容包括()。",[289,291,293,295,297],{"key":20,"text":290,"correct":22},"建筑规划",{"key":24,"text":292,"correct":26},"编制依据",{"key":28,"text":294,"correct":26},"抗震设计原则及措施",{"key":31,"text":296,"correct":26},"地质地震灾害的概况",{"key":34,"text":298,"correct":22},"全厂建筑物的情况",{"id":300,"libraryId":5,"type":15,"typeLabel":16,"stem":301,"options":302,"answer":313,"analysis":37},940852,"下列关于工程方案及配套工程方案的说法，正确的有()。",[303,305,307,309,311],{"key":20,"text":304,"correct":22},"维修设施属于厂外配套工程",{"key":24,"text":306,"correct":26},"坚持尽量依托社会力量配套服务的原则",{"key":28,"text":308,"correct":26},"水利工程的坝体建筑结构属于生产工艺方案",{"key":31,"text":310,"correct":22},"应充分利用当地材料，谨慎采用新结构、新构件、新材料",{"key":34,"text":312,"correct":26},"位于工业园区的工程建设项目应优先考虑依托园区公用工程岛供应水、电、汽、热","BCE",{"id":315,"libraryId":5,"type":40,"typeLabel":41,"stem":316,"options":317,"answer":20,"analysis":37},940853,"关于建设项目供电工程方案设计的说法，正确的是()。",[318,320,322,324],{"key":20,"text":319,"correct":26},"供电系统设计需要考虑功率因数的补偿",{"key":24,"text":321,"correct":22},"供电电源应优先考虑自备电厂供电方案",{"key":28,"text":323,"correct":22},"配电方案应由电力系统统一设罝",{"key":31,"text":325,"correct":22},"高压、低压供电的变配电不应分开设罝",{"id":327,"libraryId":5,"type":40,"typeLabel":41,"stem":328,"options":329,"answer":24,"analysis":37},940854,"下列关于厂外配套工程方案设计的表述，错误的是()。",[330,332,334,336],{"key":20,"text":331,"correct":22},"厂外配套工程的确定与厂址选择密切相关",{"key":24,"text":333,"correct":26},"厂外配套工程方案设计不包括厂外通讯线路等工程的设计",{"key":28,"text":335,"correct":22},"厂外配套工程原则上尽量依托社会力量解决或通过市场运作",{"key":31,"text":337,"correct":22},"大型的供水工程需要由专业的咨询机构完成",{"id":339,"libraryId":5,"type":40,"typeLabel":41,"stem":340,"options":341,"answer":28,"analysis":37},940855,"关于项目可行性研究环境保护内容的说法，正确的是()。",[342,344,346,348],{"key":20,"text":343,"correct":22},"可行性研究不应受环评批复文件的影响",{"key":24,"text":345,"correct":22},"环境质量现状分析只考虑项目界区内",{"key":28,"text":347,"correct":26},"环境保护编制内容中应说明环保投资",{"key":31,"text":349,"correct":22},"环境保护编制内容不应考虑环境监测",{"id":351,"libraryId":5,"type":15,"typeLabel":16,"stem":352,"options":353,"answer":364,"analysis":37},940856,"项目的融资渠道分析应包括的内容有()。",[354,356,358,360,362],{"key":20,"text":355,"correct":26},"政府资金介入的必要性和可能性分析",{"key":24,"text":357,"correct":26},"吸收其他不同渠道资金的必要性和可能性分析",{"key":28,"text":359,"correct":26},"提出资金构成的建议",{"key":31,"text":361,"correct":22},"社会资金介入的必要性分析",{"key":34,"text":363,"correct":22},"提出资金去向的建议","ABC",{"id":366,"libraryId":5,"type":15,"typeLabel":16,"stem":367,"options":368,"answer":379,"analysis":37},940857,"下列费用中，应计入经营成本的有()。",[369,371,373,375,377],{"key":20,"text":370,"correct":22},"流动资金借款利息",{"key":24,"text":372,"correct":22},"建设投资借款利息",{"key":28,"text":374,"correct":26},"外购燃料费用",{"key":31,"text":376,"correct":26},"外购动力费用",{"key":34,"text":378,"correct":22},"摊销费","CD",{"id":381,"libraryId":5,"type":40,"typeLabel":41,"stem":382,"options":383,"answer":20,"analysis":37},940858,"下列选项中，属于盈利能力分析中的静态指标的是()。",[384,386,388,390],{"key":20,"text":385,"correct":26},"经济增加值",{"key":24,"text":387,"correct":22},"项目投资财务内部收益率",{"key":28,"text":389,"correct":22},"项目资本金财务内部收益率",{"key":31,"text":391,"correct":22},"项目财务净现值",{"id":393,"libraryId":5,"type":40,"typeLabel":41,"stem":394,"options":395,"answer":24,"analysis":37},940859,"下列指标中，属于财务生存能力分析指标的是()。",[396,397,398,399],{"key":20,"text":190,"correct":22},{"key":24,"text":192,"correct":26},{"key":28,"text":188,"correct":22},{"key":31,"text":400,"correct":22},"资产负债率",{"id":402,"libraryId":5,"type":40,"typeLabel":41,"stem":403,"options":404,"answer":28,"analysis":37},940860,"建设项目经济评价中，费用效果分析基本指标是()。",[405,407,409,411],{"key":20,"text":406,"correct":22},"费用效果比",{"key":24,"text":408,"correct":22},"经济净现值",{"key":28,"text":410,"correct":26},"效果费用比",{"key":31,"text":412,"correct":22},"经济内部收益率",{"id":414,"libraryId":5,"type":15,"typeLabel":16,"stem":415,"options":416,"answer":427,"analysis":37},940862,"在投资项目可行性研究中，投资估算的作用包括（ ）。",[417,419,421,423,425],{"key":20,"text":418,"correct":26},"投资决策的依据之一",{"key":24,"text":420,"correct":26},"制定项目融资方案的依据",{"key":28,"text":422,"correct":26},"进行项目财务分析、经济分析的基础",{"key":31,"text":424,"correct":26},"编制初步设计概算的依据",{"key":34,"text":426,"correct":22},"进行项目社会效益分析的依据","ABCD",{"id":429,"libraryId":5,"type":15,"typeLabel":16,"stem":430,"options":431,"answer":440,"analysis":37},940863,"下列指标中，属于盈利能力分析的动态指标的是（ ）。",[432,434,435,437,439],{"key":20,"text":433,"correct":22},"总投资收益率",{"key":24,"text":190,"correct":26},{"key":28,"text":436,"correct":26},"净现值",{"key":31,"text":438,"correct":22},"利息备付率",{"key":34,"text":196,"correct":22},"BC",{"id":442,"libraryId":5,"type":15,"typeLabel":16,"stem":443,"options":444,"answer":455,"analysis":37},940864,"文教卫生项目经济评价以经济分析为主，常用的方法有()等。",[445,447,449,451,453],{"key":20,"text":446,"correct":26},"最小成本分析",{"key":24,"text":448,"correct":22},"最大效果分析",{"key":28,"text":450,"correct":22},"经济费用效益分析",{"key":31,"text":452,"correct":26},"经济费用效果分析",{"key":34,"text":454,"correct":22},"财务可持续性分析","AD",{"id":457,"libraryId":5,"type":15,"typeLabel":16,"stem":458,"options":459,"answer":470,"analysis":37},940865,"政府投资建设的社会公益性项目可行性研究的内容，除投资项目的一般研究内容外，还应研究()。",[460,462,464,466,468],{"key":20,"text":461,"correct":26},"政府投资的必要性",{"key":24,"text":463,"correct":22},"项目的外部配套条件",{"key":28,"text":465,"correct":22},"政府投资的偿还方式",{"key":31,"text":467,"correct":26},"项目实施代建制方案",{"key":34,"text":469,"correct":26},"政府投资的出资方式","ADE",{"id":472,"libraryId":5,"type":15,"typeLabel":16,"stem":473,"options":474,"answer":364,"analysis":37},940866,"BOT 项目的结构包括的组织有()。",[475,477,479,481,483],{"key":20,"text":476,"correct":26},"项目的发起人",{"key":24,"text":478,"correct":26},"项目的投资者",{"key":28,"text":480,"correct":26},"项目的贷款银行",{"key":31,"text":482,"correct":22},"项目的设计者",{"key":34,"text":484,"correct":22},"项目的监理单位",{"id":486,"libraryId":5,"type":40,"typeLabel":41,"stem":487,"options":488,"answer":20,"analysis":37},940867,"作为BOT项目投资者，在建立和使用现金流量模型对项目的价值和风险作出定量的分析和评价时，首要的问题是合理确定和选择反映项目风险的()。",[489,491,493,495],{"key":20,"text":490,"correct":26},"贴现率",{"key":24,"text":492,"correct":22},"临界点",{"key":28,"text":494,"correct":22},"净现值率",{"key":31,"text":496,"correct":22},"敏感度系数",{"id":498,"libraryId":5,"type":40,"typeLabel":41,"stem":499,"options":500,"answer":31,"analysis":37},940868,"关于非经营性项目财务分析的说法，正确的是()。",[501,503,505,507],{"key":20,"text":502,"correct":22},"财务分析的主要目的是为投资决策提供依据",{"key":24,"text":504,"correct":22},"营业收入首先需要补偿的费用是缴纳流转税",{"key":28,"text":506,"correct":22},"无论有无营业收入，都要进行盈利能力分析",{"key":31,"text":508,"correct":26},"单位功能建设投资是常用的比选指标",{"id":510,"libraryId":5,"type":40,"typeLabel":41,"stem":511,"options":512,"answer":20,"analysis":37},940869,"下列关于非经营项目(非盈利性)项目财务分析的表述中，正确的是()。",[513,515,517,519],{"key":20,"text":514,"correct":26},"非经营性项目财务分析的要求视项目具体情况有所不同",{"key":24,"text":516,"correct":22},"非经营性项目财务分析中效益估算只含营业收入",{"key":28,"text":518,"correct":22},"非经营性项目财务分析费用估算相对简单",{"key":31,"text":520,"correct":22},"非经营性项目财务分析不需要计算指标",{"id":522,"libraryId":5,"type":40,"typeLabel":41,"stem":523,"options":524,"answer":28,"analysis":37},940870,"BOT 类项目核心是在自有资金到位的前提下，以()作为抵押，向银行换取项目所需的资金，用于项目的投资建设。",[525,527,529,531],{"key":20,"text":526,"correct":22},"项目所有权",{"key":24,"text":528,"correct":22},"特许权协议",{"key":28,"text":530,"correct":26},"项目未来的现金流",{"key":31,"text":532,"correct":22},"项目发起人的信用",{"id":534,"libraryId":5,"type":40,"typeLabel":41,"stem":535,"options":536,"answer":31,"analysis":37},940871,"对于有营业收入的非经营性项目，以营业收入补偿费用的一般顺序是()。",[537,539,541,543],{"key":20,"text":538,"correct":22},"支付运营维护成本、偿还利息、缴纳流转税、计提折旧",{"key":24,"text":540,"correct":22},"支付运营维护成本、缴纳流转税、计提折旧、偿还利息",{"key":28,"text":542,"correct":22},"缴纳流转税、支付运营维护成本、计提折旧、偿还利息",{"key":31,"text":544,"correct":26},"支付运营维护成本、缴纳流转税、偿还利息、计提折旧",{"id":546,"libraryId":5,"type":40,"typeLabel":41,"stem":547,"options":548,"answer":28,"analysis":37},940872,"可行性研究及其报告的内容和侧重点，具有明显的行业特点。农业开发项目项目层评价（ ）。",[549,551,553,555],{"key":20,"text":550,"correct":22},"只进行财务分析",{"key":24,"text":552,"correct":22},"只进行经济分析",{"key":28,"text":554,"correct":26},"以经济分析为主，财务分析为辅",{"key":31,"text":556,"correct":22},"以财务分析为主，经济分析为辅",{"id":558,"libraryId":5,"type":40,"typeLabel":41,"stem":559,"options":560,"answer":24,"analysis":37},940874,"并购项目评价的核心内容之一是()，这是决定并购企业股权转让价格的关键。",[561,563,565,567],{"key":20,"text":562,"correct":22},"并购成本分析",{"key":24,"text":564,"correct":26},"并购企业价值评估",{"key":28,"text":566,"correct":22},"并购企业自身的效益",{"key":31,"text":568,"correct":22},"并购后的协同效应分析",{"id":570,"libraryId":5,"type":40,"typeLabel":41,"stem":571,"options":572,"answer":20,"analysis":37},940875,"()是需先将某一行业按规模分类，然后计算各时期不同规模企业所占份额及其变化，以此判断拟建项目规模的效率和生存能力。",[573,575,577,579],{"key":20,"text":574,"correct":26},"生存技术法",{"key":24,"text":576,"correct":22},"规模效果曲线法",{"key":28,"text":578,"correct":22},"经验法",{"key":31,"text":580,"correct":22},"德尔菲法",{"id":582,"libraryId":5,"type":15,"typeLabel":16,"stem":583,"options":584,"answer":455,"analysis":37},940876,"下列影响项目选址的区域因素中，属于集聚因素的有()。",[585,587,589,591,593],{"key":20,"text":586,"correct":26},"有集中供热设施",{"key":24,"text":588,"correct":22},"工程地质良好",{"key":28,"text":590,"correct":22},"当地民众支持",{"key":31,"text":592,"correct":26},"有区域污水处理厂",{"key":34,"text":594,"correct":22},"上游企业就近供应原料",{"id":596,"libraryId":5,"type":15,"typeLabel":16,"stem":597,"options":598,"answer":313,"analysis":37},940877,"集聚因素是项目选址应关注的区域因素之一，集聚效应可带来的好处有()。",[599,601,603,605,607],{"key":20,"text":600,"correct":22},"延长产品生命周期",{"key":24,"text":602,"correct":26},"资源共享",{"key":28,"text":604,"correct":26},"节约投资",{"key":31,"text":606,"correct":22},"降低劳动力成本",{"key":34,"text":608,"correct":26},"缩短建设周期",{"id":610,"libraryId":5,"type":15,"typeLabel":16,"stem":611,"options":612,"answer":263,"analysis":37},940878,"投资项目总图运输方案设计中竖向布置的具体工作包括()。",[613,615,617,619,621],{"key":20,"text":614,"correct":22},"确定厂区绿化方案",{"key":24,"text":616,"correct":22},"确定厂区运输方案",{"key":28,"text":618,"correct":26},"确定建筑物的标高",{"key":31,"text":620,"correct":22},"确定场地功能区划",{"key":34,"text":622,"correct":26},"确定场地排水方式",{"id":624,"libraryId":5,"type":15,"typeLabel":16,"stem":625,"options":626,"answer":637,"analysis":37},940879,"地震安全性评价报告应当包括()。",[627,629,631,633,635],{"key":20,"text":628,"correct":26},"地震地质灾害评价",{"key":24,"text":630,"correct":26},"地震活动环境评价",{"key":28,"text":632,"correct":26},"地震地质构造评价",{"key":31,"text":634,"correct":22},"工程建设诱发地震的可能性",{"key":34,"text":636,"correct":26},"设防烈度或者设计地震动参数","ABCE",{"id":639,"libraryId":5,"type":15,"typeLabel":16,"stem":640,"options":641,"answer":652,"analysis":37},940880,"下列因素中，属于确定项目建设规模时应考虑的主要因素有()。",[642,644,646,648,650],{"key":20,"text":643,"correct":22},"项目组织与实施机构的组成",{"key":24,"text":645,"correct":26},"市场容量和竞争力",{"key":28,"text":647,"correct":26},"环境容量和自然资源供应量",{"key":31,"text":649,"correct":26},"技术条件",{"key":34,"text":651,"correct":26},"经济社会条件","BCDE",{"id":654,"libraryId":5,"type":15,"typeLabel":16,"stem":655,"options":656,"answer":427,"analysis":37},940881,"合理经济规模的衡量指标有()。",[657,659,661,663,665],{"key":20,"text":658,"correct":26},"单位产品投资",{"key":24,"text":660,"correct":26},"单位产品成本",{"key":28,"text":662,"correct":26},"劳动生产率",{"key":31,"text":664,"correct":26},"单位投资的利润",{"key":34,"text":666,"correct":22},"单位产品运营费用",[668,671,674,677,680,683],{"id":40,"name":669,"category":7,"favorite":670},"领导干部任职前廉政法规知识测试题",92,{"id":672,"name":673,"category":7,"favorite":40},595,"建筑结构与设备",{"id":675,"name":676,"category":7,"favorite":40},715,"招标采购专业知识与法律法规",{"id":678,"name":679,"category":7,"favorite":40},848,"市政方向-通用基础",{"id":681,"name":682,"category":7,"favorite":8},534,"BIM工程师",{"id":684,"name":682,"category":7,"favorite":8},535]