[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941940":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941940,608,2,"多选题","项目后评价信息数据依据中，项目策划和决策的主要文件包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","前期分析评价文件",true,{"key":16,"text":17,"correct":14},"B","有关决策部门的审批文件",{"key":19,"text":20,"correct":21},"C","工程设计文件",false,{"key":23,"text":24,"correct":21},"D","招标文件",{"key":26,"text":27,"correct":14},"E","项目评估报告","ABE","考点:项目后评价的依据。项目策划和决策的主要文件：前期分析评价文件；有关决策部门的审批文件；有关批复文件；项目评估报告。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]