[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941927":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941927,608,1,"单选题","下列选项中，不属于项目初步设计（含概算）主要内容及批复意见主要内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经济评价",true,{"key":16,"text":17,"correct":18},"B","初步设计批复意见",false,{"key":20,"text":21,"correct":18},"C","工程特点",{"key":23,"text":24,"correct":18},"D","主要技术标准","考点:项目建设全过程回顾与评价。项目初步设计（含概算）主要内容及批复意见（大型项目应在初步设计前增加总体设计阶段）。主要包括：工程特点、工程规模、主要技术标准、主要技术方案、初步设计批复意见。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]